Reclamation of the Parfenovo MSW Landfill

Reclamation of the Parfenovo MSW Landfill
Landfill reclamation for the Parfenovo MSW landfill
Customer
Monolithic Construction Management-1 JSC
Implementation dates
2020-2022 гг.
Location
Moscow Region, Sergiyevo-Posadsky Urban District, Parfenovo village
Object dimensions
16 Га
  • Tasks
    • Reduction of atmospheric pollutant emissions
    • Protection of groundwater from contamination
    • Keeping the landfill within the boundaries of the designated site
    • Prevention of landfill leachate formation
    • Efficient biogas removal
    • Landscaping and greening of the reclaimed landfill.
    Solution
    • Construction of a landfill protective barrier using geosynthetic materials («Gidrox», «Geomembrane Type 4/2», bentonite mat «Bentotech»). To prevent landfill leachate from entering groundwater, a cutoff sheet-pile wall is installed around the landfill perimeter, embedded into the aquiclude and made of profiled PVC geosheet pile «TechPolymer»
    • Construction of a reinforced-soil retaining wall reinforced with «RD Geogrid», using «Stabigrunt» material for slope stabilisation
    • Construction of a drainage system for the collection and removal of biogas using vertical «TechPolymer» drains
    • Construction of a system for the collection and conveyance of leachate, including treatment facilities
    • Construction of a system for the conveyance, storage and treatment of stormwater, including stormwater storage tanks
    • Site improvement and landscaping.